04 / INDICATIVE ROADMAP

Use the estimate as a planning range, not a fixed promise.

Per process, phases total about 16–23 weeks if run back to back. The upper range of discovery allows for December absences; phases may overlap where dependencies allow, but approval gates stay explicit.

Weeks (sequential, upper estimate)
Discover & map
4–8 weeks
RACI & owners
2–3 weeks
DMAIC improvement
6–8 weeks
SOPs, KPIs & sign-off
4 weeks

Dark bar = lower estimate; light extension = upper estimate (e.g. December absences, data readiness).

Phase 1

Discover & map

4–8 weeks (estimate)

Confirm scope, interview teams, map current process, validate systems and pain points. Upper range allows for December absences.

Phase 2

RACI & owners

2–3 weeks (estimate)

Validate decision roles, handoffs, process owner and escalation path.

Phase 3

DMAIC improvement

6–8 weeks (estimate)

Baseline, analyze causes, test change options and agree control design.

Phase 4

SOPs, KPIs & sign-off

4 weeks (estimate)

Approve documentation, metric dictionary and ERP-ready requirements.

Planning notes
  • December absences, stakeholder availability, data readiness and system integration may extend duration.
  • Technical review by Mohammad and process selection confirmation by Hanan are prerequisites to committing dates.
  • Run the interim M&E reporting cycle in parallel; do not wait for the end of process mapping.
  • Plan a later wave only after Wave 1 capacity and lessons are reviewed.

Planning gates

Gate 1 · Scope

CEO confirms initial processes, sponsor, process owner and expected deliverables.

Gate 2 · Design

Department heads validate AS-IS, RACI, TO-BE, controls and KPI definitions.

Gate 3 · Digitalize

IT confirms feasibility, security and data access; pilot users test ERP workflows and automated reports.